Najua nyinyi ni wazee kwa hivyo mmepitia mengi. Sasa niko na swali kwa wenye mmeinvest kwa property.

Kujenga apartment block ya 5 floors kwa 50*100 huchukua how long (actual building after completing land acquisition and construction paperwork)?? Najua hakuna exact time but a rough estimate ndio nataka kujua tuu.

Kupata paperwork hutake how long assuming already uko na kiwanja?? Again, nataka tu a rough estimate of the time najua it varies from case to case.

Najua mtaniuliza mbona siulizi professionals. The reason is that I need some basic information first before approaching any professional in the near future. I consider your opinions as important basic knowledge but not professional advice.
 
Last edited:

shocks

Elder Lister
Najua nyinyi ni wazee kwa hivyo mmepitia mengi. Sasa niko na swali kwa wenye mmeinvest kwa property.

Kujenga apartment block ya 5 floors kwa 50*100 huchukua how long (actual building after completing land acquisition and construction paperwork)?? Najua hakuna exact time but a rough estimate ndio nataka kujua tuu.

Kupata paperwork hutake how long assuming already uko na kiwanja?? Again, nataka tu a rough estimate of the time najua it varies from case to case.

Najua mtaniuliza mbona siulizi professionals. The reason is that I need some basic information first before approaching any professional in the near future. I consider your opinions as important basic knowledge but not professional advice.
Architectural & Structural (yours truly) designs + kanjo approval 2-3 months. Lakini I've seen design stage drag for over six months due to client changing his mind. Cost ya approval is dependant on development size, they estimate your construction cost then pro rate the approval fee, 1% in Nairobi then uongeze a few thousands for the site board and hoarding. The below was for a approximately 3,000SQ.M development in Nairobi.
IMG_20210329_002832.jpg

Designs zikiisha and while waiting for kanju engage a Q.S, afanye breakdown and cashflow analysis for your construction. His document, called a B.o.Q will allow you to negotiate with a contractor, or with material procurement if you are building yourself.

Utatafuta contractor during this period while seeking approvals. Ukipata kanjo approval rush to Nema and have your contractor go to NCA. 2-3weeks.

Enabling works, excavation and sub-structure. Start excavation with temporary approvals (an excavation permit) as you await the approval process incase zichelewe. Hapa it really depends on site conditions. I've seen sites that have taken 2 weeks from site handover to first concrete pour ilhali kuna sites that have taken 3 months plus due to ground water, excavation of hard rock, cutting black cotton soil, shoring and protection of neighbouring buildings e.t.c. Important sana, check levels so that you can drain storm water and sewer, I've seen a building where ground floor toilets were below sewer line invert level. Then do your setting out accurately, kuna nyumba where walijenga kwa plot ya jirani. ikiwa site ni tricky, surveyor ata ku sort.

Super structure - hapa sasa timelines depend on your cash flow. Normally a floor slab a month, but you can do every fortnight tho you will require lots more formwork and labour. For you hapa ni 3-5 months.

Finishes, hapa ndipo kazi iko, na ni kazi that requires very serious supervision na haiwezi harakishwa. if your cash flow allows don't wait to finish the structure to start this off. When you are done with a level anza plaster, weka door and window frames, plumbing weka e.t.c

To answer your question, ipatie 9 months optimistic, a year ukipatana na challenges.
 
Last edited:

mzeiya

Elder Lister
Architectural & Structural (yours truly) designs + kanjo approval 2-3 months. Lakini I've seen design stage drag for over six months due to client changing his mind. Cost ya approval is dependant on development size, they estimate your construction cost then pro rate the approval fee, 1% in Nairobi then uongeze a few thousands for the site board and hoarding.

Designs zikiisha and while waiting for kanju engage a q.s, afanye breakdown and cashflow analysis for your construction. His document, called a B.o.Q will allow you to negotiate with a contractor, or with material procurement if you are building yourself.
Utatafuta contractor during this period while seeking approvals. Ukipata kanjo approval rush to Nema and have your contractor go to NCA. 2-3weeks.

Enabling works, excavation and sub-structure. Start excavation with temporary approvals (an excavation permit) as you await the approval process incase zichelewe. Hapa it really depends on site conditions. I've seen sites that have taken 2 weeks from site handover to first concrete pour ilhali kuna sites that have taken 3 months plus due to ground water, excavation of hard rock, cutting black cotton soil, shoring and protection of neighbouring buildings e.t.c. Important sana, check levels, so that you can drain storm water and sewer, I've seen a building where ground floor toilets were below sewer line invert level.

Super structure - hapa sasa timelines depend on your cash flow. Normally a floor slab a month, but you can do every fortnight tho you will require lots more formwork and labour. For you hapa ni 3-5 months.

Finishes, hapa ndipo kazi iko, na ni kazi that requires very serious supervision na haiwezi harakishwa. if your cash flow allows don't wait to finish the structure to start this off. When you are done with a level anza plaster, weka door and window frames, plumbing weka e.t.c

To answer your question, ipatie 9 months, give or take.
Brilliant.
Brilliant response.
 

bigDog

Elder Lister
Najua nyinyi ni wazee kwa hivyo mmepitia mengi. Sasa niko na swali kwa wenye mmeinvest kwa property.

Kujenga apartment block ya 5 floors kwa 50*100 huchukua how long (actual building after completing land acquisition and construction paperwork)?? Najua hakuna exact time but a rough estimate ndio nataka kujua tuu.

Kupata paperwork hutake how long assuming already uko na kiwanja?? Again, nataka tu a rough estimate of the time najua it varies from case to case.

Najua mtaniuliza mbona siulizi professionals. The reason is that I need some basic information first before approaching any professional in the near future. I consider your opinions as important basic knowledge but not professional advice.
Paper work takes roughly 3 months. You will approvals from your county government, Nema, NCA. Note that you might even need to make a change of use if the area is a non commercial zone.

Generally, structural works (masonry) costs the same in a given zone. A two bedroom house with the same design costs the same whether it's in Umoja or Kiambu town. The cost difference is caused by finishing. Hapo ndiyo autatoa jasho. A well finished two bedroom apartment will cost you at least 2m. Five floors in a 50x100 will have about 20 apartments if the ground floor is used as parking space. Make it 24 apartments if you don't require parking space.

Work with professionals mtu yangu. Never let anything to chance, everything must be planned on paper before you implement it on site. Never ever let your fundis to think for you. Hire professionals to do that. Get a good site supervisor and insulate him from money issues.
 

Pamba 1

Elder Lister
Paper work takes roughly 3 months. You will approvals from your county government, Nema, NCA. Note that you might even need to make a change of use if the area is a non commercial zone.

Generally, structural works (masonry) costs the same in a given zone. A two bedroom house with the same design costs the same whether it's in Umoja or Kiambu town. The cost difference is caused by finishing. Hapo ndiyo autatoa jasho. A well finished two bedroom apartment will cost you at least 2m. Five floors in a 50x100 will have about 20 apartments if the ground floor is used as parking space. Make it 24 apartments if you don't require parking space.

Work with professionals mtu yangu. Never let anything to chance, everything must be planned on paper before you implement it on site. Never ever let your fundis to think for you. Hire professionals to do that. Get a good site supervisor and insulate him from money issues.