Some illumination on the Kenya electricity conundrum...

Mwalimu-G

Elder Lister
(c&p from Nation)

How too much energy generation short-circuited Kenya Power
Tuesday, August 25, 2020
bulb.jpg

Ambitious electricity production without a clear cut route to increase in demand triggered trouble for Kenya Power's monopoly.
File | Nation Media Group
edwinokoth.jpg

By Edwin Okoth
What you need to know:
  • In the year to June 2020 alone, data shows that Kenya Power bought 11,462 gigawatt-hours (GWh) and managed to sell just 8,773GWh.
  • By 2026, the Energy and Petroleum Regulatory Authority, says demand supply gap is expected to rise from a deficit of 104MW in 2019 to 923MW.
Sometimes in 2013, a plan was hatched to raise Kenya’s installed generation capacity to 6,762 megawatts in just 40 months.
As to who would consume the power and whether the ultimate goal would end up with cheaper electricity to consumers, was not given much thought and seven years later, the scheme has short circuited Kenya’s single off-taker for electricity-Kenya Power

The Jubilee Administration’s plans to add 5,000MW to the country’s electricity generation was one of the most criticised ambitions but it pushed on anyway.
The argument then was that Kenya was going to grow industries, have an electric train on the standard gauge railway line, build resort cities and establish several special economic zones with huge demand for power.
With the ambitious projections in place, the government went on a deal signing spree, bringing on board independent power producers, breaking ground for mega generation projects triggering trouble for it’s distributor, which is now stuck in a revenue and debt quagmire.

Kenya Power, which then had just 2.3 million customers, was pushed to hook more households to the grid, starting with every primary school. Lines expanded and customer numbers hit a high of 7.5 million as at June 2020.
The grid grew by over 20,000 kilometres, equivalent to building a line from Cairo to the bottom of the continent in Cape Town and back. The number of substations almost doubled and with that expansion, close to Sh200 billion was sunk.
Demand growth
By last month, Kenya had an installed capacity of 2,791.2MW and an effective generation capacity of 2,712.9MW and Kenya Power which is expected to take up the electricity and sell it has been struggling. Missing demand growth has come to haunt the 2013 ambition and the off-taker has been choked.

Power purchase agreements that are signed before generators start roaring compel Kenya Power to pay for the energy generated even if it has nowhere to sell it. The clauses known as take-or-pay in the PPAs make a sweet coating to the deals while seeking for financing and are at the centre of driving the pain of excess generation.
In the year to June 2020 alone, data shows that Kenya Power bought 11,462 gigawatt-hours (GWh) and managed to sell just 8,773GWh.
miriu.jpg

Sondu- Miriu hydroelectric power plant in Nyakach Constituency in Kisumu.
File | Nation Media Group
The excess power was still paid for either way and although Covid-19 may have added to the woes, analysts blame the underlining miscalculation that failed to link increased supply with real demand for the woes now bedevilling the utility firm.
“For every megawatt generated from a plant, you need 20 times in demand but Kenya missed that widely. It’s like hiring an expensive car which you are required to pay for per day and then failing to travel or just making short trips around the town. You will still pay the renting fees anyway. Another person who hires a smaller car, pays smaller rent fees and travels a longer distance gets value for money,” energy expert Jabal Hindapal told Smart Business.
Several confidential documents shared among energy stakeholders including the regulator, the Ministry of Energy and Kenya Power show that the government failed in the demand projection, which had been pegged on projects such as an electric train that never materialised and given that the deals to generate power were already signed, the elephant in the room is far from the exit.


Projections show that the total energy purchased is expected to grow by approximately 2.3 percent this year which is much lower compared to the historical 10-year average of 5.9 percent.
The prevailing economic conditions, which have constrained household income, increased grid defections which will continue hurting supply and improved cost of solar which is pushing many to the off -grid solutions are part of the reasons demand will remain depressed.
By 2026, the Energy and Petroleum Regulatory Authority, says demand supply gap is expected to rise from a deficit of 104MW in 2019 to 923MW, against the slow growth in peak demand from the current 1,926MW in 2019 to 2,766.
This will worsen matters for Kenya Power which will have to pay for the excess capacity and whose infrastructure remain underutilised from poor growth in demand after expanding the network over the years.
Generators who supply Kenya Power with electricity it is unable to sell, say they are not to blame since they only entered into energy provision deals after the government projected that the economy would need the huge levels of power they were asked to produce.
The Electricity Sector Association of Kenya (ESAK) which brings together independent power producers (IPPs), project developers and other stakeholders working across generation, transmission in Kenya says the government would have had a better projection on demand before it went on PPA signings which essentially tie both the power business no matter the situation.

Generate power
ESAK board member and solar firm, SOWITEC managing director George Aluru said the take-or-pay deals the generators signed with Kenya Power also compel producers to pay the utility firm when they fail to generate power hence it ‘cuts both ways.’
“One would expect that demand forecasting is best done by the government and which then informs Kenya Power on what level of commitment to make with the generators over a defined period of time because the government has more role to play in determining demand. Power generation is capital-intensive and takes time as well so probably it would have been worse had we been talking about deficits. The secret now though lies on how to increase demand,” Mr Aluru said.

Demand according to him should be able to meet projections the government had when it had envisioned the generation including the special economic zones, the industrial parks and the smart cities such Konza.
The government plan to generate over 5000MW in four years also pushed Kenya Power into short-term debt to finance its infrastructure expansion to be ready to distribute what is generated.
The firm’s debt stock has hit Sh102.6 billion and is required to meet a yearly debt service obligation of Sh2.4 billion. Kenya Power can hardly pay for the electricity supplied to it by the generators including the Kenya Electricity Generating Company (KenGen) which it now owes some Sh23.7 billion (some of which continue to accrue interest).

The off-taker spent some Sh123.2 billion in connecting more customers to the grid as the government sought to have more households supplied with electricity especially before the last General Elections.
To add insult to injury, the majority of ew connections involved those in rural areas where demand is low while the cost of maintenance is very high due to the extensive distribution lines.
The latest survey by the Kenya National Bureau of Statistics shows that revenues from rural electrification continue to decline even as the number of households connected rose.
“The number of customers connected under the rural electrification programme expanded by 5.8 percent to 1,409,256 in 2018/19 from 1,332,209 in the 2017/18, mainly drawn from domestic and small commercial categories. However, revenue realised declined by 9.1 percent from Sh11.84 billion in 2017/18 to Sh10.77 billion in 2018/19,” said the KNBS in the 2020 Economic Survey.
77,047 customers
The report essentially shows that Kenya Power connected 77,047 more customers in rural areas during the year but collected Sh1.07 billion less.
Some rural and urban poor who are unable to meet the power costs resort to illegal connections that bypass the meters whenever they are disconnected for failing to purchase top ups-increasing non-technical losses for Kenya Power.


While the overall goal of the ambitious 2013 plan was to make power available and reduce the cost to consumers, it worked in reverse. Increasing technical losses due to underutilised infrastructure is now set to cost consumers some Sh6 billion every year as the government adjusted recoverable losses from 14.9 percent to 15.9 percent.
The government also left a huge transmission gap despite channeling lots of efforts to the generation, which essentially meant Kenya Power would not receive the energy it has signed to pay for due to lack of transmission lines.
On a live television debate on Thursday, Kenya Electricity Transmission Company Managing Director Fernandes Barasa said the Sh18 billion Olkaria-Lessos-Kisumu transmission line would now wait until 2021.
The project has been delayed for years and after a lengthy wayleave row with the Kedong Ranch management and owners of another parcel of land in Kisumu’s Mambo Leo, the ministry of Energy had estimated its completion date to be September 2020.
January was the sixth change of timeline for the project whose delay has starved western Kenya of adequate power supply from the cheaper geothermal power from Olkaria, resulting in a suppressed demand and denying Kenya power and opportunity to sell electricity.

The 300-kilometre Olkaria-Lessos-Kisumu line runs from Naivasha steam fields through Eldoret to the lakeside city of Kisumu and is expected to spur industrial growth in western parts of the country as well as stabilise supply in the region now reliant on the diesel run generator at Muhoroni and imports from Uganda.
The line was originally expected to be completed in February 2018, then it was pushed forward by a year to early 2019 due to funding and wayleave hurdles. By May 2019, the project was said to have been 80 percent complete as KETRACO changed its timeline to March 2020 and later to July 2020.
Western Kenya and parts of Nyanza homes and businesses experience frequent power outages due to reliance on the 65MW kerosene powered generator in Muhoroni.

The Japanese funded project (through JICA) comprising a 400, 220 and 132KV network has been the missing link between the region and the idle power at Olkaria.
Power demand
Western Kenya and the North Rift in 2018 recorded almost a double increase in power demand. South Nyanza in particular doubled its electricity demand for the domestic load from 51-Gigawatt hours (GWh) to 106GWh. Similar increases were recorded in the small commercial load (34-54GWh) and the large commercial and industrial load(35-49GWh).

More transmission lines would also give Kenya an opportunity to export power to other countries that may need it including South Africa whose deficit is now nearing 2000MW.
The lessons are yet to sink though if recent plans by the government are to go by. The Nuclear Power and Energy Agency last week submitted impact studies for a Sh500 billion power plant which is set to generate another 1000MW by 2035.
NuPEA said it was assessing technologies “to identify the ideal reactor for the country,” it said in the report submitted to the National Environmental Management Authority.
A 2000MW coal power plant was also recently frozen in court after the government pushed forward with the plan despite environmental concerns.
The continued drive to generate power without plans on how to sell it is expected to drive Kenya Power to the edge and with it, an entire economic engine since struggling Kenya power will not even be able to keep its customers on supply let alone meet new connections.
[email protected]
 
Lessons to be learnt from Ghana’s excess electricity shambles
August 5, 2019 4.02pm SAST
Author
  1. Samuel Asumadu Sarkodie
    Research fellow, Nord University


file-20190801-169696-vehmvu.jpg


Electricity pylon. Wikimedia Commons

Access to energy plays a critical role in economic development. But bad government policies have affected energy security in many developing countries.
It is estimated that two out of three households (almost 600 million people) in sub-Saharan Africa have no access to electricity. Ghana has also had its challenges. A shortage of generating capacity led to rationing in 2014 and 2015, with serious consequences for the economy.
Nearly five years later the country faces the exact opposite problem: excess electricity. Ghana’s Finance Minister Ken Ofori-Atta set out the scale of the problem in his mid-year review budget on July 29. He said that the problem posed grave financial risks to Ghana’s economy. This is because the government is carrying legacy debt in the energy sector, which threatens to put a huge strain on its finances.
According to Ofori-Atta, plans have been put in place to deal with the challenges in the energy sector. A recommendation has since been made to Parliament to support the renegotiation of all take-or-pay contracts to take-and-pay.
How did Ghana move from not having enough power five years ago, to being burdened with a massive energy bill as well as too much electricity?
At the heart of Ghana’s problem was how it responded to the power shortages in 2014. These hit the economy hard, leading to the mining and manufacturing sectors contracting, and unemployment going up. To address the problem, the government fast-tracked private power plants. The current glut in electricity – as well as the cost overheads – can be attributed directly to the way in which the contracts were drawn up.
Ghana’s experience is a cautionary tale for countries that find themselves in a situation of having too much electricity at any given point. Without careful forward planning, proper data-driven analysis, and transparent, competitive, corruption-free contracting processes, any country could find itself in the same situation as Ghana.
Emergency power producers
Due to challenges with public financing of energy infrastructural projects, many countries – including Ghana – have been turning to the private sector for investment in the energy sector. As a result independent power producers are receiving much more attention on the continent.
At the heart of Ghana’s energy sector challenges were the take-or-pay contracts signed by the government. To address the shortfalls it was facing, it contracted three emergency power producers during the 2014 - 2017 period. The contracting was done without a competitive process. On top of this the government signed 43 power purchase agreements.
But the demand for electricity never went up at the anticipated rate due to tariff increases and slow economic growth. As a result, the plants ended up producing excess capacity. The installed capacity according to the Energy Commission of Ghana is 5,083 MW, almost double the peak demand of 2,700 MW. Of this, 2,300 MW has been contracted on a take-or-pay basis. This means that Ghana is contractually obliged to spend money for excess capacity that’s not being consumed.
The result is that the government is paying over US$500m (almost Ghana Cedis 2.5 billion) annually for power generation capacity that’s not being used.
There is also an overhang for gas. And because the government contracted gas supply on a take-or-pay basis, it must pay whether the gas is utilised or not. Thus, from 2020, if nothing changes, Ghana will face annual excess gas capacity charges of between US$550 and US$850 million yearly. This is even after the current government terminated two other liquefied natural gas contracts in 2017.
Independent power producers
Ghana’s excess electricity problem – and its solution – boils down to the arrangements made with independent power producers.
The contracting process failed to avoid a number of pitfalls. These included:
  • A lack of flexibility in contracts. The terms and conditions are often difficult to change once purchase power agreements are signed because of a fear of putting off future investors.
  • Fixing prices in foreign currency exchange, typically US dollars.
  • Threatening competition. According to a World Bank report, independent power producers often suffocate competition once in operation. There is huge potential for inefficiencies if the independent power producers meet a large share of the load.
  • Inflated prices: the World Bank report argues that independent power producers often inflate supply prices for utilities, which raises end-user prices.
  • Currency risk protection: unlike other foreign investments, investors in independent power producers are often shielded from currency risk. Most negotiate take-or-pay contracts where all the power generated must be bought whether needed or not. Because payments are made in dollars, this becomes more like international debt than equity investment.
  • Corruption. This often creeps in when the stakes are high in contract negotiations. They are often done secretly and only become visible when there is a change of government. As the Public Services International Research Unit puts it: “Establishing power generation in excess of the country’s requirements is a feature associated with corruption ….if the process provides an income source for those negotiating the contracts”.
  • Political expediency. According to a Business Insurance report “the fundamental problem with creating independent power producers in developing countries is that initially it is based on political expediency. These things sometimes bear no relation to economic reality.”
Independent power producers have contributed immensely to Ghana’s quest to meet its power generational capacity. But lessons from Ghana’s excess electricity challenges show that unless negotiations are done with utmost transparency and care, agreements that are struck can pose financial risks and breed corruption.
This precautionary principles would save many countries from experiencing the same fate as Ghana.

Reproduced from The Conversation
 
Thanks for the insights. I was about to sink a considerable investment into clean energy but I'll have to consult further.

The essence of any successful business is to identify demand and seek to fulfill it.
 
Back
Top